Central Railway (CR) has been consistent in its efforts to provide better services to its passengers. Infrastructure works are being carried out on various sections in order to increase the speed of trains. These include multitracking (laying of multiple tracks in a section), Over Head Equipment regulation, Signalling works and other technical works.
In order to ensure safety of running trains and better riding comfort for passengers, the tracks are being maintained to the best of standards and replacement of old age assents is also being undertaken. Central Railway is way ahead of proportionate targets for track maintenance and track renewals and plans to surpass all targets for 2023-24.
These works have enabled CR to run trains on these sections at a speed of 130 kmph.
Section | Distance |
Pune – Daund Section – | 75.59 kms |
Itarsi -Nagpur-Wardha- Ballarshah Section- | 509.05 kms |
Wardha-Badnera Section | 95.44 kms |
Igatpuri-Nashik-Bhusaval- | 526.65 kms |
Total | 1206.73 kms |
Work is in progress for running of trains at 130 kmph on the following sections
Daund-Solapur-Kalaburagi-Wadi Section – | 337.44 kms |
In addition, speed has also increased from 75 kmph to 110 kmph on the Puntamba-Shirdi section of 17kms and from 65 kmph to 90 kmph on the Badnera-Amravati section of 9 kms.
Apart from these, there are plans to increase speed of trains in the following sections:
Badnera-Chandur Bazar section of 42 kms from 100 kmph to 110 kmph
Majri-Wani-Pimpalkhuti section of 79 kms & Paraisia-iChhindwara section of 29 kms from 50 kmph to 110 kmph
Jalamb-Khamgaon section of 12 kms from 60 kmph to 90 kmph.
In Mumbai Suburban section plans to increase speed of trains is as follows:
Tilak Nagar- Panvel section of 33 kms, Thane-Vashi section of 18 kms & Nerul-Kharkopar section of 9 kms from 80 kmph to 105 kmph
Karjat-Khopoli section of 15 kms from 60 kmph to 90 kmph
Removing of Permanent Speed Restrictions (PSR) by improving track geometry have also facilitated increase of speed of trains on Central Railway. A total of 9 PSRs have been removed as on 30.11.2023 and work of removing more is in progress.
The speed of trains have been increased after ensuring all safety aspects and technical inspection by the concerned officials. This will decrease running time of trains and improve overall punctuality of train movements.
Central Railway is committed to provide a safe and pleasant journey to its commuters and has been tirelessly working to ensure the same.